Forthcoming Works

You will see the building take shape quickly now.

The programme is to have the first floor completed during September and the second floor completed at the start of October.

The substructure’s blockwork will be continuing at ground floor level for the next couple of weeks, followed by the installation of the ground floor slab later in September.

Fusion lightweight frame works will continue to the second floor during this month.